What a great task list looks like

Est. 0.5 h · estimate · draft

A worked, fully fictional example: replacing a pressure transmitter. Every craft, support crew, hold point and wait is its own line, in the order the work really happens.

DRAFT Generic example data only. Field names, control keys and screen layout Unverified

Criticality / urgencyLowMediumHigh / safety
Separate from criticalityPlanner's Edge: best practice, cost saving, wrench-time gain
IA13Display Functional Location Task List: Operation OverviewMOCKUP
Functional loc. PLANT-A-UNIT-1-PT101 Pressure transmitter PT-101 (example)
Group 1000001 Counter 1
Plant 1000
Usage 4 Plant maintenance
Status 4 Released (general)
Planner group P01
ActSOpWork ctrPlntCtrl keyDescriptionNo.Dur.WorkUnitCK%Activity typeCost elem.Pur. grpMat. grp
10010OPS-011000PM01Lead call: job walk, permit request, JSA review11.01.0H1LAB-OPS
20020OPS-011000PM01Ops make ready: isolate, drain, depressure, LOTO22.04.0H1LAB-OPS
0030MECH-011000PM01Decon / vac truck assist to clear impulse lines21.53.0H1LAB-MECH
0040INST-011000PM01Disconnect transmitter wiring; tag and terminate11.01.0H1LAB-INST
0050INSUL-011000PM01Remove insulation / jacketing at transmitter21.02.0H1LAB-INSUL
0060HTRC-011000PM01Remove heat trace; megger and record as-found11.01.0H1LAB-ELEC
30070MECH-011000PM01Pull transmitter and manifold; blind open ends22.04.0H1LAB-MECH
40010CRANE-011000PM02↳ Sub-op: crane support for removal11.01.0H162xxxxP10CRANE
0020RIG-011000PM01↳ Sub-op: rigging / signal person21.02.0H1LAB-RIG
50080QC-011000PM01QC: inspect flange faces, record as-found10.50.5H1LAB-QC
0090MECH-011000PM01Transport removed unit to shop10.50.5H1LAB-MECH
60100LAG1000PM03External lag: vendor bench / replacement lead time024.00.0H0P10SERVICE
0110MECH-011000PM01Install new transmitter and manifold; new gaskets and bolting to spec22.04.0H1LAB-MECH
0010CRANE-011000PM02↳ Sub-op: crane support for install11.01.0H162xxxxP10CRANE
0020RIG-011000PM01↳ Sub-op: rigging / signal person21.02.0H1LAB-RIG
50120QC-011000PM01QC/QA hold point: joint torque verified, leak test witnessed11.01.0H1LAB-QC
0130HTRC-011000PM01Reinstall heat trace; megger as-left11.01.0H1LAB-ELEC
0140INSUL-011000PM01Reinstall insulation / jacketing21.02.0H1LAB-INSUL
0150INST-011000PM01Reconnect wiring; verify terminations10.50.5H1LAB-INST
70160INST-011000PM01Loop check and calibration; record as-left11.51.5H1LAB-INST
80170OPS-011000PM01Ops return to service: remove LOTO, line up, sign-off / certify21.02.0H1LAB-OPS
Total planned work (example)35.0H
Illustrative mockup — not actual SAP software. SAP is a trademark of SAP SE. Fictional example data.

Teaching callouts

1Lead with the call and the permit

Operation 0010 makes the permit and job walk a scheduled step with an owner, not an assumption. It is the first gate every other operation waits on.

2Ops make-ready is its own operation

Isolation and LOTO belong to operations' work center so their hours show up on the schedule and capacity, instead of hiding inside the craft's time.

3Sequencing in steps of 10

Operations are numbered 0010, 0020… in the order the work happens. Gaps of 10 leave room to insert a step later without renumbering. Relationships (finish-to-start) can be added in the order for scheduling tools Unverified.

4Sub-operations for support crafts

Crane and rigging are sub-operations (SOp 0010, 0020) under the lift they support. They share the parent's timing, so support crews get booked for the same window without cluttering the main sequence Unverified.

5QC / QA hold points

Inspections are separate operations under a QC work center so they cannot be skipped and work cannot proceed until they are confirmed. The second QC step is the joint integrity hold point before heat trace and insulation cover the joint.

6External and lag operations

Operation 0100 uses an external control key and a LAG work center with zero work but 24 h duration. It holds the schedule open for a vendor or lead time without consuming in-house labor Unverified.

7Loop check closes the I&E work

Calibration and loop check are explicit with as-left records, so the job is not "done" until the signal is proven at the control system.

8End with operations accepting the equipment

Return to service and sign-off is the last operation, owned by operations. It is the handback point the scheduler confirms against.

Columns that matter

Control keyPM01 = internal labor (confirmable, costed by activity type). PM02 / PM03 = external service or purchased labor, generating a purchase requisition with cost element, purchasing group and material group Unverified.
Duration vs workWork = total labor hours (persons × duration). Duration = elapsed time. Two people for 2 h is 4 h work but 2 h duration. Schedulers plan the calendar on duration; capacity uses work. CK (calculation key) tells the system which one to derive Unverified.
Activity typeLinks an internal operation to a labor rate for cost planning (example values only: LAB-MECH, LAB-INST) Unverified.
Purchasing columnsExternal operations carry cost element, purchasing group and material group so the requisition routes to buyers without manual edits Unverified.
% (work percentage)Optional split of work across resources; often left blank on a simple list Unverified.