Resources / Template guide: Task list
Task List Template
DRAFT · unverifiedTemplate: Task List Template (Mechanical + Instrumentation & Electrical (I&E))
Version: v0.1 (DRAFT)
Date: October 25, 2026
Publisher: The Planner's Bench
Status: DRAFT. All technical content is Unverified until the owner signs off (Playbook DRAFT v0.2, rule 2). Employer rule (Playbook v0.2, rule 6) applied: public sources only.
Files: task-list-template.csv (the sheet) and this README.
Source keys: [S#] and [map X] are public sources, listed with their URLs under Sources at the end.
Purpose
Use this sheet to draft or review a preventive maintenance (PM) task list before you build or change it in SAP Plant Maintenance (SAP PM). It puts every operation, its work center, duration, package, parts and readings on one page so you, the supervisor and the craft can review it before it goes into the system.
How to use
- Open
task-list-template.csv(comma-separated values) in Excel or Google Sheets. Delete the "Header note" rows at the top before you sort or import. Delete the rows marked "Example data" when you start your own list, or keep them on a separate tab for reference. - Fill in the header fields once per task list (columns A–I). Repeat them on every row so the sheet can be filtered and sorted.
- Add one row per operation. Number operations in steps the way your site does (the example uses 0010, 0020).
- Write the operation text so a technician knows what to check, the limit, and what to record. Avoid "inspect as required."
- For strategy plans, assign each operation to a maintenance package (e.g., 1M, 3M, 6M). For single-cycle plans, leave the package blank and put the cycle in the header.
- List components that are always needed for that operation. Check them against the equipment bill of materials (BOM).
- Fill in the "Interval source" column for every safety-critical or regulatory operation (e.g., safety instrumented system (SIS) proof tests). The interval comes from the requirement, not from habit.
- Review the sheet with the supervisor and a craft representative, then build or change the task list in SAP PM using the transactions in the Fields table.
- Your site's configuration, procedures, permit rules and management of change (MOC) process override this template.
Fields
| Column | Field | Meaning | Related SAP transaction or field | Source |
|---|---|---|---|---|
| (top) | Header note | Draft status, version, disclaimer and owner (5 rows). Delete before use | none, sheet control | n/a |
| A | Row type | "Example data" for sample rows; leave blank for your rows | none, sheet control | n/a |
| B | Task list type | Equipment, functional location (FL), or general task list | IA01, Create Equipment Task List; IA11, Create Functional Location Task List; IA05/IA06, Create/Change General Maintenance Task List; IA09, Display Task Lists | [map A] [map E] [S3] |
| C | Equipment / FL | Object the task list belongs to (blank for a general task list) | IE03, Display Equipment; IL03, Display Functional Location; IH01, Functional Location Structure | [map B] [map E] [S3] |
| D | Task list description | Short title of the task list | Task list header | [S3] |
| E | Planning plant | Plant that plans the work | Task list header | [S3] |
| F | Planner group | Planner group responsible | Task list header | [S3] |
| G | Strategy | Maintenance strategy for strategy plans (blank for single-cycle) | IP11, Create/Change Maintenance Strategies; IP12, Display Maintenance Strategies | [map D] [map C] [S1] [S2] |
| H | Plan type (intended) | Single-cycle, strategy, or multiple counter plan that will call this task list | IP41, Create Single-Cycle Plan; IP42, Create Strategy Plan; IP43, Create Multiple Counter Plan | [map F] [S8] [S2] |
| I | Discipline | Mechanical, Instrumentation, Electrical, or Multi-craft | none, planning field | n/a |
| J | Operation no. | Operation number in sequence | Task list operation | [S3] |
| K | Operation short text | One-line description of the operation | Task list operation | [S3] |
| L | Operation long text | What to check, the limit, what to record | Task list operation | [S3]; content Unverified |
| M | Work center | Craft work center that performs the operation | IR03, Display Work Center (IR01/IR02 to create/change) | [map B] [S3] |
| N | No. of people | Number of people needed | Task list operation | [S3] [UNVERIFIED: field name] |
| O | Duration (hrs) | Time per person for the operation | Task list operation ("time required") | [S3] |
| P | Package | Maintenance package for strategy plans (e.g., 1M, 3M) | Operation-to-package assignment | [S1] [S2] [S4] |
| Q | Running or shutdown | Whether the equipment can run during the operation | none, planning field | n/a Unverified |
| R | Component material no. | Spare part or material always needed | Task list operation components; IB01, Create Equipment BOM | [S3] [map B] |
| S | Component qty | Quantity per operation | Task list operation components | [S3] |
| T | Measuring point | Reading to record (vibration, temperature, as-found, counter) | IK01, Create Measuring Point; IK03, Display Measuring Point | [map B] |
| U | Acceptance limit | Limit for the reading, from OEM, site standard or safety requirement | none, non-system field | TBD: owner to supply |
| V | Safety-critical? | Yes if the operation tests a safety or regulatory function | none, planning field | [S5] [S6] [S7] |
| W | Interval source | Where the interval comes from (e.g., safety requirements specification (SRS), original equipment manufacturer (OEM) manual, code, site standard) | none, non-system field | [S5] [S6] [S7] |
| X | Permit / isolation notes | Permit types and isolation the operation needs, per site rules | none, non-system step | [S15] |
| Y | Review notes | Feedback from techs and reviewers | none, review field | n/a |
Craft notes: Our transaction reference pairs strategy and multiple counter plans (IP42, IP43) mostly with Mechanical work, such as pump packages or run hours, and single-cycle plans (IP41) mostly with I&E (Instrumentation & Electrical) work, such as fixed-interval calibration [map F] Unverified. Your site may differ. Mechanical rows usually carry more components (seals, bearings, gaskets). I&E rows usually carry as-found/as-left readings, calibration equipment, and bypass or electrical isolation notes.
Worked example
task-list-template.csv contains two example task lists, both labeled "Example data" in column A:
- Mechanical: an equipment task list for a fictional centrifugal pump (P-0000A) on a strategy plan with 1M/3M/6M packages.
- I&E: an equipment task list for a fictional pressure transmitter (PT-0000) in a safety instrumented function, on a single-cycle plan.
Equipment numbers, material numbers, work centers, durations and intervals in the examples are fictional and illustrative. They are not recommendations Unverified. Pump-specific details have no public source and are illustrative only Unverified.
Confidentiality
Everything in this template is built from public sources (listed below) and general industry knowledge. It contains no employer or client documents, procedures, data, equipment tags, site names or branding. Equipment numbers, work centers and plant codes in the examples are made up. [EMPLOYER REVIEW: owner to check that the column layout, operation wording and example structure don't mirror any employer's internal task list standard.]
Disclaimer
Adapt to your site's SAP configuration and procedures. Not affiliated with or endorsed by SAP SE.
© TBD: owner to supply year [PLACEHOLDER: legal entity]. The Planner's Bench is a brand of [PLACEHOLDER: legal entity].
SAP and SAP PM are trademarks of SAP SE. Educational content only. Follow your site's procedures, permit and isolation rules, OEM guidance and applicable codes and standards.
Sources
- [S1] SAP Help, Maintenance Strategy (PM): https://help.sap.com/doc/saphelp_nw70/7.0.12/ja-JP/3c/abaf72413911d1893d0000e8323c4f/content.htm
- [S2] SAP Learning, Using Maintenance Plans: https://learning.sap.com/courses/exploring-business-processes-in-sap-s-4hana-asset-management/using-maintenance-plans_ebb53721-acf1-4f60-9207-3b17091fa1d7-1-1
- [S3] SAP Learning, Using Maintenance Task List: https://learning.sap.com/courses/exploring-business-processes-in-sap-s-4hana-asset-management/using-maintenance-task-list_d763c67c-2b76-4916-9aab-4625c59c09f6-1-1-1
- [S4] SAP Community, Strategies and plans: https://community.sap.com/t5/enterprise-resource-planning-q-a/strategies-and-plans/qaq-p/6330079
- [S5] IChemE, Proof Testing (paper 67): https://www.icheme.org/media/15519/paper-67.pdf
- [S6] Emerson, Ensuring safety compliance with optimized proof testing: https://www.emerson.com/is/content/emerson/en/corporate/shared-assets/documents/ensuring-safety-compliance-with-optimized-proof-testing.pdf
- [S7] SINTEF PDS, Guideline for follow-up of SIS in the operating phase (2021): https://pds-forum.com/wp-content/uploads/2022/09/SINTEF-pds-report-guideline-for-follow-up-of-sis-in-the-operating-phase-2021-edition.pdf
- [S8] / [map F] SAP Learning, Using SAP GUI-Based Functions for Single-Cycle Plans: https://learning.sap.com/courses/exploring-preventive-maintenance-in-sap-s-4hana-asset-management/using-sap-gui-based-functions-for-single-cycle-plans
- [S15] Occupational Safety and Health Administration (OSHA) 29 CFR 1910.147, Control of Hazardous Energy (lockout/tagout (LOTO); US general industry only): https://www.osha.gov/laws-regs/regulations/standardnumber/1910/1910.147
- [map A] https://spendwizard.com/sap-tutorial/sap-pm-tcodes/
- [map B] https://erp-docs.com/wp-content/uploads/2024/01/sap-pm-important-tcode-for-master-data-maintenance.pdf
- [map C] https://sapstack.com/pm/sap-pm-transaction-codes/
- [map D] https://s4-experts.com/sap-pm-transaction-codes/
- [map E] https://community.sap.com/t5/enterprise-resource-planning-blog-posts-by-members/standard-sap-plant-maintenance-reports/ba-p/13300346
Verification log
- Verified by: [owner] | Date: [ ] | Notes: [ ]